This new item is an update to the £5m unitized facade package in central London.
We have been working on this project for the last 7 months. Carefully managing and negotiating the design development process with the Main Contractor and the Architect to achieve the design intent whilst carefully managing our client’s budget.
We have also overseen the procurement and scheduling process. Manufacture of unitized frames commenced some months ago.
The steel frame is now progressing and should be complete in early 2014. The first delivery of unitized frames complete with Portland stone are scheduled to be delivered to site from the European manufacturing facility in January.
We have been in discussions with the Main Contractor for some months regarding the specific logistics required for a central London unitized project of this nature.
We will update more information on this project as on-site erection progresses.