The project is now fully complete and the building occupied. All unitised frames up to level 11 are now installed and complete. The prefabricated balconies to the south elevation have now been installed and associated rainwater system incorporated into the unitised perimeter pressings has been connected and tested. The bespoke unitised rain screen vertical fin system to level 12 and 13 roof level, despite a number of installation challenges, has been installed and the roof area executive function room is now occupied.
The ground floor grids stick and Boon Edam glass revolving door have been installed and commissioned.
From the attached photographs the completed project is a fantastic looking building, one Integral Management are proud to have provided project management service for.