Walkabout News - Integral successfully manage site challenges

Walkabout News – Integral successfully manage site challenges

We have now been working on this project for 4 months

Despite the challenges of COVID-19, and other site challenges we have been able to successfully manage the installation programme, to date 75 % of the project is now installed and glazed

The bespoke feature fin and ventilation grill profile to the head of the north and south curtain walling frames is due on site at the end of February, which will complete the frames to these elevations

The 6 story curtain walling screen to the front elevation is now also installed and will shortly be glazed with the assistance of an Oscar 280 glazing robot

The ground floor east elevation has a number of areas where both vertical and sloped curtain walling will be installed, including the curved head feature main entrance screen along with vertical and roof glazing to the new Café entrance. Due to the availability of the structure these elements are not planned to be installed until May 21

The completed façade will not be visible until the sheeted scaffolding is removed in the next few months

Back to News