Oxford University Biochemistry Phase 2 – Challenging times through the Coronavirus pandemic

Congratulations to Laing O`Rourke`s site management team for the way they have kept everyone safe which has allowed the project to progress safely during the COVID19 pandemic. There have been challenging delays with the procurement of materials, we experienced some suppliers closing their doors for a number of weeks, stopping deliveries to site altogether. The installation teams work force has had to be reduced to ensure safe social distancing c...read more »

Deansgate Manchester nears completion

The demise of the main contractor and 4 weeks away from site plus the Coronavirus pandemic has meant an inevitable delay to the end date for this project. However, the new main contractor has worked diligently to keep the project on track. Extra works have been added taking the package value over £10m. Big thanks to our client's site management team for their endurance to keep the standards high in challenging circumstances. We believe this is ...read more »

Oxford University Biochemistry Phase 2

Integral Management have been providing project management services to deliver the external façade package at the above new build project. Laing O’Rourke have been working on the Oxford University campus for several years delivering a number of design award winning buildings for the University over this period.   The façade is an extension to phase 1 and therefore needed to match phase 1 in as many aspects as possible. This presented...read more »

Deansgate Manchester

125 Deansgate has been a very challenging project for both Integral Management and our client. The main façade package was completed in August 2019. However due to a number of unforeseen circumstances the programme for the main construction works has been extended to April 2020. We have been on site completing various elements and extra works on and off in over the last months. We are now in the final throws of managing the last elements of...read more »

Integral New Project in Manchester

With a change of geographical location, Integral have been asked to provide project management services to this striking building in the heart of Manchester's commercial district. Manchester has an incredible ongoing regeneration programme. Some 60 tower cranes can presently be seen at any one time on the Manchester skyline. The facade package totally encloses the perimeter of the building from ground floor level to level 11, equating to ...read more »

Slough School Project Update

Of the three new build school schemes within the original package, one is nearing completion. Due to the variety of external cladding materials we have been reliant upon other sub-contractors completing their packages before the curtain walling screens within these phases can be finally completed. The last phase of the two remaining schools are planned for completion in September 2017. We will post more photos of the complete elevations nearer th...read more »

Installation progressing at R1 Kings Cross

The external precast stone facade is programmed to be complete by the end of August 2017. The unitised window frames are progressing well, being installed from level 1 up the facade of the building, installed into fully prepared openings within the precast stone. Curtain walling grid work to level 1 and 2 atrium terrace area and ground floor on the north elevation is also well underway. ...read more »

£1bn Regeneration Project in Slough

Integral are proud to be asked to be part of a £1bn regeneration scheme for Slough town centre. A good façade Client we have worked with successfully in the past asked us to Project Manage the design, procurement and delivery of the external glazing packages for three new build school schemes with Morgens Sindall, in Slough. The Curtain walling package worth over £500k is now on site and is due to be completed in June 2017...read more »

Integral manage external blind refurbishment at Leicester University Building

Integral have been asked to manage the refurbishment and replacement of a number of Schuco blinds to the external façade of a new faculties building on the Leicester University campus. Access was the main challenge, we used a number of specialist access options including very large cherry pickers. With the expertise of the installation team all work was successfully completed in February 2017....read more »

R1 Kings Cross London

With the success of previous projects we are delighted to continue the ongoing relationship with this unitised curtain walling company, and their fourth building in this regeneration area with the same Developer. This prestigious signature building has a very individual design and will provide a state of the art learning environment for the ever increasing local student population. With nearly 250 no bespoke pre-glazed unitised windows, and over...read more »